Pre-Feasibility Study for the Establishment of a Solid Waste Recycling Plant

Year: 1995
Type: article
Abstract: This Pre-feasibility Study Final Report sets out, inter alia, an assessment of the proposed establishment of a recycling plant to be carried out in the vicinity of Caboolture Shire, south-east Queensland. The capital required to fund the Project is $20m, with the base model assuming that 80% ($16m) is derived from investors, and the balance ($4m) obtained through debt funding. This will support capital works in the order of $18m, and a further $2m working capital. The "Break-Even" point is reached where the amount received for MSW Garbage is $34.60 per tonne (assuming 100% equity / investor) funding. The Project will take approximately four years (from the commencement of the commercialisation stage) to achieve annual profitability.