Work

Results of Cavity Series Fabrication at Jefferson Laboratory for the Cryomodule R100

Year: 2011
Type: article
Abstract: A series production of eight superconducting RF cavities for the cryomodule R100 was conducted at JLab in 2010. The cavities underwent chemical post-processing prior to vertical high power testing and routinely exceeded the envisaged performance specifications. After cryomodule assembly, cavities were successfully high power acceptance tested. In this paper, we present the achievements paving the way for the first demonstration of 100 MV (and beyond) in a single cryomodule to be operated at CEBAF.
Language: English
Open Access status: green
OpenAlex ID: W187606252
FWCI: 0.121
Cites:
Cited by: 3
Related to: 10