Work

Monitoring the Capability of Production Equipment in Organization

Year: 2014
Type: article
Abstract: This work is focused on determining the capability of production equipment in Volkswagen Slovakia, a.s. during the moulding of a car door. There were taken 150 samples from the moulding process that followed each other. Values were recorded on a Wenzel RAplus 1625 measuring machine. Subsequently, process stability was verified. It showed that measured values had a stable average value, and the process did not show irregularities in the diagrams of the X card and s card. After verification of stability, the values of C m and C mk were calculated, which exceeded the minimum requirement of 1.66 and 1.67, and the requirements for the capability of production equipment have thereby been met.
Language: English
Open Access status: gold
Estimated APC paid: $215
OpenAlex ID: W2014132310
FWCI: 0.309
Cites: 4
Cited by: 7
Related to: 10