Analysis of SIEMENS 3AQ1-EE breaker double trip blocking inspection circuit

Year: 2009
Type: article
Abstract: The paper introduces basic fundamental and practice problem of electric power system relay protection double configuration. It particularly expatiates on characteristic and shortcoming of SIMES’s 3AQ1-EE breaker trip blocking inspection circuit. It also analyzes and discusses implement technique combining with the alterations of SIEMENS’s 3AQ1-EE breaker double trip blocking inspection circuit in some transformer substations, and brings forward some implement points and solving project for the alteration implement project.