Discussion about replacement scheme for 110 kV substation DC system
Year: 2010
Type: article
Abstract: For single charging supply and single charger of DC system in a 110 kV substation integrated automation, it will subject to disappear or the switch will miss trip when DC power supply is replaced. This paper plans for finding a way out of the difficulties through a temporary DC system and the existing DC systems operate in parallel. By test, temporary DC system is built, implement process of DC reconstruct is made, and circulations caused by parallel operation are solved.
Author: Kai Xu
Language: Chinese
Subfield: Electrical and Electronic Engineering
Field: Engineering
Domain: Physical Sciences
Keywords: 110 kV substation, DC power supply system
Open Access status: diamond