Abstract: For single charging supply and single charger of DC system in a 110 kV substation integrated automation, it will subject to disappear or the switch will miss trip when DC power supply is replaced. This paper plans for finding a way out of the difficulties through a temporary DC system and the existing DC systems operate in parallel. By test, temporary DC system is built, implement process of DC reconstruct is made, and circulations caused by parallel operation are solved.