An optimal recursive search procedure for the deterministic unconstrained max-nvp project scheduling problem
Year: 1996
Type: report
Abstract: The deterministic unconstrained max-npv problem involves the scheduling of the activities of a project in order to maximize its net present value.Projects are assumed to be represented by an activity network in activity-on-the-node format.Activities have a known deterministic duration and are subject to zero-lag finish-start precedence constraints.Cash flows are assumed to be known in both their amount and timing.Progress payments and cash outflows are made upon the completion of certain activities.The project is to be scheduled subject to a fixed deadline in the absence of resource constraints.We describe a new optimal procedure which performs a recursive search on partial tree structures based on the fundamental logic that positive cash flows should be scheduled as early as possible while negative cash flows should be scheduled as late as possible within the precedence constraints.The procedure has been coded in Visual C++, version 2.1 for use on a personal computer.Encouraging computational results obtained on two data sets confirm that the search procedure outperforms an adapted version of the procedure which was previously developed by Grinold for projects in activity-on-the-arc format. (Project Scheduling -Discounted cash flows; Net Present Value; Optimal search)
Source: Lirias (KU Leuven)
Author: Erik Demeulemeester
Language: English
Field: Decision Sciences
Domain: Social Sciences
Open Access status: green
OpenAlex ID: W252542259