Abstract: The first Wave Dragon prototype power production testing started May 2003 and ended temporarily primo 2005. In the mentioned period Wave Dragon was situated in a corner of Nissum Bredning with relative little amount of wave energy. Main purpose of the tests was demonstration of survivability and availability.