Work

Improvements to the Recycler/Main Injector to Deliver 850 kW+

Year: 2022
Type: article
Abstract: The Main Injector is used to deliver a 120 GeV high power proton beam for Neutrino experiments. The design power of 700 kW was reached in early 2017 but further improvements have seen a new sustained peak power of 893 kW. Two of the main improvements include the shortening of the Main Injector ramp length as well optimizing the slip-stacking procedure performed in the Recycler to reduce the amount of uncaptured beam making its way into the Main Injector. These improvements will be discussed in this paper as well future upgrades to reach higher beam powers.
Language: English
Open Access status: green
OpenAlex ID: W4318339536
FWCI: 0.111
Cites:
Cited by: 2
Related to: 10