Rethinking Schedule Quality Risk Assessment

Year: 2025
Type: article
Abstract: Critical Path Method schedule reliability is dependent on exhibition of specific qualities. Failure to exhibit these qualities (i.e., schedule defects) increases project risk exposure. Although current schedule quality assessment methods provide diagnostic remediation insights, they do not provide a meaningful singular assessment value that characterizes the nature and magnitude of schedule quality risk nor do they enable parity when comparing schedule quality across multiple schedules of disparate size (e.g., number of tasks) or complexity (e.g., number of concurrent paths, degree of merge bias). This study employed a design science research approach to address current schedule quality assessment practice dilemmas through proposition of a new methodological artifact for evaluating schedule quality risk.