Visual Evaluation of Construction Schedule Progress by Linking Photographs and 4D Model
Year: 2026
Type: article
Abstract: During the construction period, numerous site photographs are routinely captured; however, their use is largely limited to simple visual inspection of construction status. To enhance the practical utilization of such photographic information, this study proposes a 4D-based construction progress management system that visually evaluates schedule progress by integrating site photographs within a BIM-based information management framework. The proposed system synchronizes site photographs with corresponding 4D model images using coordinate linkage and applies deep learning–based object detection to identify matching construction elements. Construction progress is approximately estimated by analyzing bounding box overlap between detected elements in site photographs and planned elements in 4D model images. A case study conducted on a bridge construction project demonstrated that the trained model achieved an overall [email protected] of 0.532, and that the proposed method enables intuitive and approximate progress evaluation. The results indicate that the proposed system can improve the usability of site photographs as supporting information for 4D-based construction progress management.
Source: Buildings
Authors: Sang-Mi Park, JaeHee Lee, Leen-Seok Kang
Language: English
Subfield: Building and Construction
Field: Engineering
Domain: Physical Sciences
Open Access status: gold
Estimated APC paid: $3,137
Award: G6338148576
OpenAlex ID: W7128709132