A Shorter Simulation Horizon for the Cyclicity of Periodic Real-Time Schedules

Year: 2026
Type: conference-abstract
Abstract: We address the cyclicity of schedules and strictly improves the well-known Leung and Merrill 1980 result, (Omax + 2H), where (H = LCM(periods)). We show that the bound can be reduced tomax{0, max{O_i - T_i} + H(1+U), where (U) is the processor utilization. Thus, in the common case where (O_i < T_i), the bound is simply (H(1+U)). We also show that when building a schedule, we can stop at the first idle point strictly after max{0-, max{Oi-Ti}}+H, which is the end of the cyclic par of the schedule.