AIB Data Centers Moves 50 MW CLT1 Campus Forward with Secured Prepayment and Equipment Orders in South Carolina, US
Year: 2026
Type: article
Abstract: In parallel, the company placed purchase orders for backup generators, uninterruptible power supply (UPS) systems, and switchgear, with deliveries scheduled to align with the construction timeline of its U.S. data center projects. The company expects CLT1 to deliver 50 MW of critical IT capacity under an executed 12-year customer agreement.