Rice Supply Chain Risk Analysis Using the House of Risk (hor) Method at Spb Makassar, Regional Industrial Business Unit Iii, Perum Bulog

Year: 2026
Type: article
Abstract: Purpose: This study aims to identify priority risks and risk agents in rice distribution process activities at SPB Makassar, Regional Industrial Business Unit III, Perum BULOG, and to determine strategic response plans to reduce the potential occurrence of risks in rice distribution activities at SPB Makassar, Regional Industrial Business Unit III, Perum BULOG. Design/Methodology/Approach: This study uses a descriptive quantitative approach to analyze and minimize risks in the supply chain at SPB Makassar through the application of the House of Risk (HOR) method. Findings/Results: HOR Phase I identified 12 risk events and 12 risk agents. Based on the ARP calculation and Pareto diagram, all risk agents were within the 80% cumulative threshold and were therefore prioritized for mitigation. The dominant risk agents included inaccurate route assessment, vehicle inspection, order matching, final inspection, cargo security, vehicle scheduling, and staff absence. HOR Phase II. Based on the priority risk agents, 7 preventive actions were formulated through brainstorming with experts. Each action was assessed based on Total Effectiveness (TEk), Difficulty, and Effectiveness to Difficulty Ratio (ETDk). The strategy with the highest ETDk value was prioritized because it was considered the most effective relative to its implementation difficulty. Implications: The main implication of this study is the provision of more focused risk priorities and mitigation strategies, enabling BULOG to implement preventive actions more effectively and support the smoothness of the rice distribution process. Conclusion: The identification results show 12 activities, 12 risk events, and 12 risk agents in rice distribution. HOR Phase I established three priority risk agents based on the highest ARP values, namely A12 (378), A7 (324), and A3 (315). HOR Phase II generated 7 mitigation actions, with three main priorities: route inspection (PA1; TEk 3,402), vehicle inspection using a checklist (PA2; TEk 2,916), and order data verification (PA3; TEk 2,835).
Language: English
Open Access status: diamond
OpenAlex ID: W7233522108
FWCI:
Cites:
Cited by:
Related to: 10