A multi-disciplinary assessment of operator action time for mitigating a postulated accident

Year: 1992
Type: article
Abstract: This report discusses mitigation of the postulated Loss of Heat Sink Accident for the Savannah River Site K Reactor which requires operator action to place the plant in a water conservation configuration. In August 1991, concerns were raised about the allowances in the safety analyses for operator action times in an unpowered scenario, where several valves would be manually closed. WSRC management conservatively decided to include explicit consideration of a seismic initiator for this scenario, which introduced the additional concern that operator actions could be hindered by tritium from flange leakage. The revised analyses concluded that the powered case documented in the Safety Analysis Report is limiting and that all acceptance criteria are met.